Measure, do not guess
Two weeks of observation and data before a single recommendation.
Projects were landing late without anyone able to say where the time went. The studio suspected the tools. It was not the tools.
We measured before recommending. Two weeks of shadowing and timesheet analysis found that most of the loss sat in three handovers, not in anyone working slowly.
Two weeks of observation and data before a single recommendation.
Three named handover points with a checklist each. The most common rework cause disappeared.
A short list people would actually adopt, reviewed after a month.
Revision rounds per project fell by roughly a third within two months. The studio kept four of the five changes.